5 Steel Frame |
||||||||||||
|
The main halls of the complex will be supported by a wide steel frame, positioned on the newly levelled foundations. |
||||||||||||
|
|
Sections of steel frame were delivered and cemented into the levelled foundation area. |
|
The completed frame covers the area of halls one and two of the new complex. |
|||||||||
|
Meanwhile excavation continued at the rear of the site for the lower level rooms The soil removed is very chalky. |
|
The foundation is prepared for the lower rooms which will adjoin the undercroft rooms. |
|
|||||||||